... ... @@ -54,11 +54,12 @@
54 54  *** Configure your DHCP server software to assign IP addresses in the desired range
55 55  *** Once the processor is assigned an IP address, connect to it via Text Console at the assigned IP address
56 56  *** Run the above commands to disable DHCP and assign a static IP address to the processor
57 -* For processors with a Control Subnet (CP3N/AV3/PRO3/CP4N/AV4/PRO4/ZUM-HUB4), additional setup is required
57 +* For processors with a Control Subnet (CP3N/AV3/PRO3/CP4N/AV4/PRO4), additional setup is required
58 58  ** Connect to the processor via Text Console and run the command: ##startprogafterrouter on##
59 59  *** This will force the processor to wait until the router has started before attempting to load the showrunner™ program, avoiding potential license validation issues if the processor boots up before the router.
60 60  ** The previously listed "ipa," "ipm," etc. commands will configure settings for the processor's LAN port, which should be connected to the building LAN or third party network.
61 -** Lighting control hardware (e.g. TSWs, DIN-CENCN-2s, etc.) should be connected to the Control Subnet port. The processor acts as a DHCP server on the Control Subnet, with addresses that are determined automatically based on the LAN configuration.
61 +** Lighting control hardware (e.g. TSWs, DIN-CENCN-2s, etc.) should be connected to the Control Subnet port. The processor acts as a DHCP server on the Control Subnet, with addresses that are determined automatically based on the LAN configuration. 
62 +*** Lighting hardware can be connected via the LAN port, however for proper functionality you must run the command: ##securegateway default##
62 62  ** The Control Subnet will automatically configure itself based on the LAN configuration, but it can optionally be configured manually:
63 63  *** Using the "Functions>Ethernet Addressing...>Control Subnet" menu of Toolbox:
64 64  **** Set routing to "Manual" with the start address and subnet size
... ... @@ -98,7 +98,7 @@
98 98  *** Click the "Send" button and click "Yes" to upload the program
99 99  *** Once it is done loading, you should be able to run the ##sr ver## command and see the currently installed version of SHOWRUNNER™
100 100  * Once SHOWRUNNER™ is loaded, you can connect to the UI by navigating to the processor’s IP. A license and configuration file are still required.  
101 -** **3-Series processors require authentication enabled** (SSL self can be used but steps will need to be repeated)
102 +** **3-Series processors require authentication enabled** ("##ssl self##" command followed by a reboot can be used but steps will need to be repeated)
102 102  ** If stuck on "Connecting to Processor" you will need to accept the certificate
103 103  * For jobs with multiple processors, SHOWRUNNER™ will need to be loaded to each processor