... ... @@ -1,9 +1,13 @@
1 +(% class="box errormessage" %)
2 +(((
3 +This page is for ordinary processor setup. For ZUM-HUB4 deployments, see our [[dedicated ZUM-HUB4 page>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.SHOWRUNNER™ Installation and Network Setup.ZUM-HUB4 Processor Setup.WebHome]].
4 +)))
5 +
1 1  (% class="box warningmessage" %)
2 2  (((
3 -showrunner™ is tested against current Crestron firmware releases.  Please use at least the recommended firmware builds.
8 +SHOWRUNNER™ is tested against current Crestron firmware releases.  Please use at least the recommended firmware builds.
4 4  3-Series: PUF 1.8001.0146
5 5  4-Series: PUF 2.7000.00052.01
6 -ZUM-HUB4: PUF 2.005.0056
7 7  VC-4: 2.7000.00047
8 8  )))
9 9  
... ... @@ -50,10 +50,13 @@
50 50  *** This will force the processor to wait until the router has started before attempting to load the showrunner™ program, avoiding potential license validation issues if the processor boots up before the router.
51 51  ** The previously listed "ipa," "ipm," etc. commands will configure settings for the processor's LAN port, which should be connected to the building LAN or third party network.
52 52  ** Lighting control hardware (e.g. TSWs, DIN-CENCN-2s, etc.) should be connected to the Control Subnet port. The processor acts as a DHCP server on the Control Subnet, with addresses that are determined automatically based on the LAN configuration.
53 -** The Control Subnet can be configured manually in the "Functions>Ethernet Addressing...>Control Subnet" menu of Toolbox
54 -*** Set routing to "Manual" with the start address and subnet size
55 -*** E.g., a setting of "10.0.0.0/24" will have the processor at 10.0.0.1 with an IP mask of 255.255.255.0 and a default gateway and DNS server at 10.0.0.2
56 -** The Control Subnet can also be configured to e.g. **10.0.0.0/24** using Text Console command: ##csrouterprefix **10.0.0.0/24**##
57 +** The Control Subnet will automatically configure itself based on the LAN configuration, but it can optionally be configured manually:
58 +*** Using the "Functions>Ethernet Addressing...>Control Subnet" menu of Toolbox:
59 +**** Set routing to "Manual" with the start address and subnet size
60 +**** E.g., a setting of "100.64.0.0/20" will have the processor at 10.64.0.1 with an IP mask of 255.255.240.0 and a default gateway and DNS server at 100.64.0.2
61 +*** Using Text Console commands (example for a **100.64.0.0/20** subnet, with a processor IP address of **100.64.0.1**)
62 +**** Set CS IP: ##csrouterprefix **100.64.0.0/20**##
63 +**** Reboot the processor: ##reboot##
57 57  * If the job has multiple processors, then these steps must be repeated for all processors on the job
58 58  ** For jobs with Central Control, the IP addresses of the processors matters
59 59  ** Chief Integrations will provide an SRTakeoff.xlsx spreadsheet with an IP Table tab that lists the IP address for each processor. If these IP addresses must be changed during startup, then it will be necessary to also change the IP addresses in the Remote System Definition in the configuration file
... ... @@ -62,7 +62,7 @@
62 62  === Program Load ===
63 63  
64 64  * Download the latest build of SHOWRUNNER™ from the[[ Chief Integrations Portal>>https://files.chiefintegrations.com/index.php/s/WHNzXrrZbB5jC3E]]
65 -* Connect your computer to the same network as the processor. Make sure your computer’s IP settings are compatible with the lighting network and do not conflict with any devices already on the network.
72 +* Connect your computer to the same network as the processor. Make sure your computer’s IP settings are compatible with the lighting network and do not conflict with any devices already on the network
66 66  ** While it is possible to load the program via USB, it is not recommended because the transfer speed is significantly slower than loading via Ethernet
67 67  * Double click the PUF to open the Package Update Tool and install SHOWRUNNER™ (works best with Toolbox closed)
68 68  ** The Package Update Tool will automatically open your Address Book and prompt you to select a device
... ... @@ -77,17 +77,18 @@
77 77  ** Run the command ##sr ver##
78 78  ** If the console returns with the newly installed version of SHOWRUNNER™, then the installation was successful
79 79  ** If the console returns with "Bad or Incomplete Command (sr)" then the installation was not successful
80 -*** Rename the .puf file to be a .zip file and open the archive
87 +*** Rename the downloaded .puf file to be a .zip file and open the archive
81 81  **** Some file archivers (such as 7-Zip) allow you to right click on the PUF file and open the archive without changing the filetype
82 82  *** Extract the "CI.Lighting.ShowRunner.cpz" file
83 -*** In Toolbox, connect to the processor via Text Console and click the lightning bolt icon and select "SIMPL Program..."
84 -*** Under the "Send" section, browse your PC and select the extracted .cpz file
90 +*** In Toolbox, connect to the processor via Text Console, click the lightning bolt icon, and select "SIMPL Program..."
91 +**** Alternatively, navigate to Functions>SIMPL Program...>SIMPL Program (Program01)...
92 +*** Under the "Send Program" section, browse your PC and select the extracted .cpz file
85 85  *** Click the "Send" button and click "Yes" to upload the program
86 86  *** Once it is done loading, you should be able to run the ##sr ver## command and see the currently installed version of SHOWRUNNER™
87 87  * Once SHOWRUNNER™ is loaded, you can connect to the UI by navigating to the processor’s IP. A license and configuration file are still required.  
88 -** **3-Series processors require authentication enabled** (SSL self can be used but steps will need to be repeated).
89 -** If stuck on "Connecting to Processor" you will need to accept the certificate.
90 -* For jobs with multiple processors, SHOWRUNNER™ will need to be loaded to each processor.
96 +** **3-Series processors require authentication enabled** (SSL self can be used but steps will need to be repeated)
97 +** If stuck on "Connecting to Processor" you will need to accept the certificate
98 +* For jobs with multiple processors, SHOWRUNNER™ will need to be loaded to each processor
91 91  
92 92  === License and Configuration Deployment ===
93 93  
... ... @@ -112,7 +112,7 @@
112 112  ***** ##sradmin username "name" administrators password##
113 113  ***** The username and password should be one word each and are the credentials used to log in to the showrunnerHUB™
114 114  ***** The name can be multiple words as long as it is in quotes, and is simply a friendly name used to identify each user.
115 -*** Once logged in to the showrunnerHUB™ UI, you should be automatically redirected to the File Management page.
123 +*** Once logged in to the showrunnerHUB™ UI, you should be automatically redirected to the File Management page
116 116  **** If you are not automatically redirected, then you can navigate to this page by clicking "Setup" in the top right and then selecting "File Management" from the list on the left
117 117  **** [[image:1654807593390-193.png]]
118 118  **** Under “Upload New License File”