1 This is a broad-strokes checklist for what needs to be completed by a technician for a ShowRunnerCLC™ startup. This checklist is not 100% comprehensive and does not go into detail for each step.
2
3 More detailed specifics and troubleshooting information are available in the [[ShowRunnerCLC™ Startup Guide>>doc:SHOWRUNNER™ Setup Guide.WebHome]].
4
5 Startup Checklist:
6
7 * Before arriving on-site:
8 ** Ensure you have the [[required tools and software>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Preparing to Go On-Site.WebHome]]
9 ** Ensure the jobsite is meets [[site readiness requirements>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Site Readiness Checklist.WebHome]]
10 * Once on-site:
11 ** Configure authentication settings for networked devices
12 ** Configure IP settings for networked devices (processors, TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.)
13 ** Configure clock and time zone for processors
14 ** Update firmware for all networked devices (excluding Zūm Net devices)
15 ** Load ShowRunnerCLC™ program, license, and configuration file to the processor
16 ** Load the ShowRunnerCLC™ UI to any touchscreens
17 ** Load the ShowRunnerCLC™ expansion program to any GLPACs
18 ** Configure the IP table for any required devices (TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.)
19 *** Ensure [[SSL Setup>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.SHOWRUNNER™ Installation and Network Setup.CEN-GWEXER Setup.WebHome||anchor="HSSLSetup"]] has been performed for devices that require it
20 ** Poll Cresnet/acquire infinetEX devices to gateways and verify devices are online in Toolbox
21 ** Assign Cresnet/RFID IDs to devices and verify they are reporting online to ShowRunnerCLC™
22 *** If necessary, update firmware for any Cresnet and RFID devices
23 ** Update firmware for Zūm Net devices
24 *** See [[Zūm Wired specific>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.SHOWRUNNER™ Installation and Network Setup.Updating Firmware.WebHome||anchor="HZ16BmWiredSpecificNotes"]] firmware notes
25 ** Verify load schedule and fixture functionality
26 *** Toggle each load individually and verify they dim and switch correctly
27 *** Verify loads are assigned to correct areas
28 *** Assign friendly load labels as necessary
29 *** Use the "Verification" checkbox to add a verified timestamp to the load
30 ** Verify occupancy sensors
31 *** Verify correct area assignments
32 *** Verify correct direct load assignments if necessary
33 *** Adjust timeouts and sensitivities as necessary
34 ** Verify keypad functionality
35 *** Verify correct area assignments
36 *** Verify correct button layouts and functionality
37 *** Configure keypad actions as necessary
38 ** Verify photocell functionality
39 *** Verify photocells respond to changes in light levels
40 *** Assign photocells to appropriate lighting zones and enable for required scenes
41 *** Adjust sensitivity as necessary
42 ** Verify partition sensor functionality
43 *** Verify correct area assignments
44 *** Adjust sensitivity as required for consistent partition detection
45 ** Configure Area-level sequence of operations
46 *** Occupancy/vacancy mode
47 *** Occupied/vacant scenes
48 *** Scene levels
49 ** Complete functionality test (QC, make sure each room functions from an end-user perspective)
50 ** Set up any schedules as required per the sequence of operations
51 ** End-user training
52 * Before leaving the site:
53 ** Make back-ups for all configurations
54 *** If using the Backup feature in ShowRunnerHUB™, be sure to record the secret used when generating the backup
55 ** Save a Device Summary using Device Discovery in Crestron Toolbox