Wiki source code of Startup Checklist
Version 6.1 by Alexander Mott on 2023/05/19 16:21
Hide last authors
| author | version | line-number | content |
|---|---|---|---|
| |
5.1 | 1 | This is a broad-strokes checklist for what needs to be completed by a technician for a ShowRunnerCLC™ startup. This checklist is not 100% comprehensive and does not go into detail for each step. |
| |
1.1 | 2 | |
| |
5.1 | 3 | More detailed specifics and troubleshooting information are available in the [[ShowRunnerCLC™ Startup Guide>>doc:SHOWRUNNER™ Setup Guide.WebHome]]. |
| |
1.1 | 4 | |
| 5 | Startup Checklist: | ||
| 6 | |||
| 7 | * Before arriving on-site: | ||
| 8 | ** Ensure you have the [[required tools and software>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Preparing to Go On-Site.WebHome]] | ||
| |
3.1 | 9 | ** Ensure the jobsite is meets [[site readiness requirements>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Site Readiness Checklist.WebHome]] |
| |
1.1 | 10 | * Once on-site: |
| |
4.1 | 11 | ** Configure IP settings for networked devices (processors, TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.) |
| |
1.1 | 12 | ** Configure clock and timezone for processors |
| 13 | ** Update firmware for all networked devices | ||
| 14 | ** If necessary, update firmware for Zūm Net and Cresnet devices | ||
| |
5.1 | 15 | ** Load ShowRunnerCLC™ program, license, and configuration file to the processor |
| 16 | ** Load the ShowRunnerCLC™ UI to any touchscreens | ||
| 17 | ** Load the ShowRunnerCLC™ expansion program to any GLPACs | ||
| |
4.1 | 18 | ** Configure the IP table for any required devices (TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.) |
| |
1.1 | 19 | ** Poll Cresnet and verify devices are online in Toolbox |
| |
5.1 | 20 | ** Assign Cresnet IDs to devices and verify they are reporting online to ShowRunnerCLC™ |
| |
1.1 | 21 | ** Verify load schedule and fixture functionality |
| |
6.1 | 22 | *** Toggle each load individually and verify they dim and switch correctly |
| |
1.1 | 23 | *** Verify loads are assigned to correct areas |
| 24 | *** Assign friendly load labels as necessary | ||
| |
6.1 | 25 | *** Use the "Verification" checkbox to add a verified timestamp to the load |
| |
1.1 | 26 | ** Verify occupancy sensors |
| 27 | *** Verify correct area assignments | ||
| 28 | *** Adjust timeouts and sensitivities as necessary | ||
| 29 | ** Verify keypad functionality | ||
| 30 | *** Verify correct area assignments | ||
| 31 | *** Verify correct button layouts and functionality | ||
| 32 | ** Verify photocell functionality | ||
| 33 | *** Assign photocells to appropriate lighting zones and enable for required scenes | ||
| 34 | *** Adjust sensitivity as necessary | ||
| 35 | ** Verify partition sensor functionality | ||
| 36 | *** Verify correct area assignments | ||
| 37 | *** Adjust sensitivity as required | ||
| 38 | ** Set up any schedules as required per the sequence of operations | ||
| |
2.1 | 39 | ** Complete functionality test (QC, make sure each room functions from an end-user perspective) |
| 40 | ** End-user training |