7 7  * Before arriving on-site:
8 8  ** Ensure you have the [[required tools and software>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Preparing to Go On-Site.WebHome]]
9 -** Ensure the jobsite is meets [[site readiness requirements>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Site Readiness Checklist.WebHome]]
9 +** Ensure the jobsite is meets [[site readiness requirements>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Site Readiness Checklist.WebHome]]
10 10  * Once on-site:
11 11  ** Configure IP settings for networked devices (processors, TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOX, etc.)
12 12  ** Configure clock and timezone for processors
... ... @@ -34,3 +34,5 @@
34 34  *** Verify correct area assignments
35 35  *** Adjust sensitivity as required
36 36  ** Set up any schedules as required per the sequence of operations
37 +** Complete functionality test (QC, make sure each room functions from an end-user perspective)
38 +** End-user training