Scott Kohlmann 5.1 1 This is a broad-strokes checklist for what needs to be completed by a technician for a ShowRunnerCLC™ startup. This checklist is not 100% comprehensive and does not go into detail for each step.
Alexander Mott 1.1 2
Scott Kohlmann 5.1 3 More detailed specifics and troubleshooting information are available in the [[ShowRunnerCLC™ Startup Guide>>doc:SHOWRUNNER™ Setup Guide.WebHome]].
Alexander Mott 1.1 4
5 Startup Checklist:
6
7 * Before arriving on-site:
8 ** Ensure you have the [[required tools and software>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Preparing to Go On-Site.WebHome]]
Alexander Mott 3.1 9 ** Ensure the jobsite is meets [[site readiness requirements>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Site Readiness Checklist.WebHome]]
Alexander Mott 1.1 10 * Once on-site:
Alexander Mott 4.1 11 ** Configure IP settings for networked devices (processors, TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.)
Alexander Mott 1.1 12 ** Configure clock and timezone for processors
13 ** Update firmware for all networked devices
14 ** If necessary, update firmware for Zūm Net and Cresnet devices
Scott Kohlmann 5.1 15 ** Load ShowRunnerCLC™ program, license, and configuration file to the processor
16 ** Load the ShowRunnerCLC™ UI to any touchscreens
17 ** Load the ShowRunnerCLC™ expansion program to any GLPACs
Alexander Mott 4.1 18 ** Configure the IP table for any required devices (TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.)
Alexander Mott 1.1 19 ** Poll Cresnet and verify devices are online in Toolbox
Scott Kohlmann 5.1 20 ** Assign Cresnet IDs to devices and verify they are reporting online to ShowRunnerCLC™
Alexander Mott 1.1 21 ** Verify load schedule and fixture functionality
Alexander Mott 6.1 22 *** Toggle each load individually and verify they dim and switch correctly
Alexander Mott 1.1 23 *** Verify loads are assigned to correct areas
24 *** Assign friendly load labels as necessary
Alexander Mott 6.1 25 *** Use the "Verification" checkbox to add a verified timestamp to the load
Alexander Mott 1.1 26 ** Verify occupancy sensors
27 *** Verify correct area assignments
Alexander Mott 7.1 28 *** Verify correct direct load assignments if necessary
Alexander Mott 1.1 29 *** Adjust timeouts and sensitivities as necessary
30 ** Verify keypad functionality
31 *** Verify correct area assignments
32 *** Verify correct button layouts and functionality
Alexander Mott 7.1 33 *** Configure keypad actions as necessary
Alexander Mott 1.1 34 ** Verify photocell functionality
Alexander Mott 7.1 35 *** Verify photocells respond to changes in light levels
Alexander Mott 1.1 36 *** Assign photocells to appropriate lighting zones and enable for required scenes
37 *** Adjust sensitivity as necessary
38 ** Verify partition sensor functionality
39 *** Verify correct area assignments
Alexander Mott 7.1 40 *** Adjust sensitivity as required for consistent partition detection
41 ** Configure Area-level sequence of operations
42 *** Occupancy/vacancy mode
43 *** Occupied/vacant scenes
44 *** Scene levels
Alexander Mott 1.1 45 ** Set up any schedules as required per the sequence of operations
Alexander Mott 2.1 46 ** Complete functionality test (QC, make sure each room functions from an end-user perspective)
47 ** End-user training