5.1 | 1 | This is a broad-strokes checklist for what needs to be completed by a technician for a ShowRunnerCLC™ startup. This checklist is not 100% comprehensive and does not go into detail for each step. |
![]() |
1.1 | 2 | |
![]() |
5.1 | 3 | More detailed specifics and troubleshooting information are available in the [[ShowRunnerCLC™ Startup Guide>>doc:SHOWRUNNER™ Setup Guide.WebHome]]. |
![]() |
1.1 | 4 | |
5 | Startup Checklist: | ||
6 | |||
7 | * Before arriving on-site: | ||
8 | ** Ensure you have the [[required tools and software>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Preparing to Go On-Site.WebHome]] | ||
![]() |
3.1 | 9 | ** Ensure the jobsite is meets [[site readiness requirements>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Site Readiness Checklist.WebHome]] |
![]() |
1.1 | 10 | * Once on-site: |
![]() |
8.1 | 11 | ** Configure authentication settings for networked devices |
![]() |
4.1 | 12 | ** Configure IP settings for networked devices (processors, TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.) |
![]() |
8.1 | 13 | ** Configure clock and time zone for processors |
14 | ** Update firmware for all networked devices (excluding Zūm Net devices) | ||
![]() |
5.1 | 15 | ** Load ShowRunnerCLC™ program, license, and configuration file to the processor |
16 | ** Load the ShowRunnerCLC™ UI to any touchscreens | ||
17 | ** Load the ShowRunnerCLC™ expansion program to any GLPACs | ||
![]() |
4.1 | 18 | ** Configure the IP table for any required devices (TSW touch panels, DIN-CENCN-2s, ZUMNET-JBOXs, GLPACs, etc.) |
![]() |
8.1 | 19 | *** Ensure [[SSL Setup>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.SHOWRUNNER™ Installation and Network Setup.CEN-GWEXER Setup.WebHome||anchor="HSSLSetup"]] has been performed for devices that require it |
20 | ** Poll Cresnet/acquire infinetEX devices to gateways and verify devices are online in Toolbox | ||
21 | ** Assign Cresnet/RFID IDs to devices and verify they are reporting online to ShowRunnerCLC™ | ||
![]() |
9.1 | 22 | *** If necessary, update firmware for any Cresnet and RFID devices |
![]() |
8.1 | 23 | ** Update firmware for Zūm Net devices |
24 | *** See [[Zūm Wired specific>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.SHOWRUNNER™ Installation and Network Setup.Updating Firmware.WebHome||anchor="HZ16BmWiredSpecificNotes"]] firmware notes | ||
![]() |
1.1 | 25 | ** Verify load schedule and fixture functionality |
![]() |
6.1 | 26 | *** Toggle each load individually and verify they dim and switch correctly |
![]() |
1.1 | 27 | *** Verify loads are assigned to correct areas |
28 | *** Assign friendly load labels as necessary | ||
![]() |
6.1 | 29 | *** Use the "Verification" checkbox to add a verified timestamp to the load |
![]() |
1.1 | 30 | ** Verify occupancy sensors |
31 | *** Verify correct area assignments | ||
![]() |
7.1 | 32 | *** Verify correct direct load assignments if necessary |
![]() |
1.1 | 33 | *** Adjust timeouts and sensitivities as necessary |
34 | ** Verify keypad functionality | ||
35 | *** Verify correct area assignments | ||
36 | *** Verify correct button layouts and functionality | ||
![]() |
7.1 | 37 | *** Configure keypad actions as necessary |
![]() |
1.1 | 38 | ** Verify photocell functionality |
![]() |
7.1 | 39 | *** Verify photocells respond to changes in light levels |
![]() |
1.1 | 40 | *** Assign photocells to appropriate lighting zones and enable for required scenes |
41 | *** Adjust sensitivity as necessary | ||
42 | ** Verify partition sensor functionality | ||
43 | *** Verify correct area assignments | ||
![]() |
7.1 | 44 | *** Adjust sensitivity as required for consistent partition detection |
45 | ** Configure Area-level sequence of operations | ||
46 | *** Occupancy/vacancy mode | ||
47 | *** Occupied/vacant scenes | ||
48 | *** Scene levels | ||
![]() |
10.1 | 49 | ** Complete functionality test (QC, make sure each room functions from an end-user perspective) |
![]() |
1.1 | 50 | ** Set up any schedules as required per the sequence of operations |
![]() |
2.1 | 51 | ** End-user training |
![]() |
11.1 | 52 | * Before leaving the site: |
![]() |
12.1 | 53 | ** Make back-ups for all configurations |
54 | *** If using the Backup feature in ShowRunnerHUB™, be sure to record the secret used when generating the backup | ||
![]() |
11.1 | 55 | ** Save a Device Summary using Device Discovery in Crestron Toolbox |
56 | ** Use Crestron's Information Tool to generate reports for all devices |