... ... @@ -7,10 +7,14 @@
7 7  * Networked control hardware (Cresnet and Zūm Wired devices) should be installed per the submittals
8 8  * Ethernet runs between control and HUB panels should be complete and terminated at the panels
9 9  * Serial numbers for installed devices should be collected and provided to the technician prior to arriving on-site
10 -* If applicable, building LAN should be up and running
10 +* If applicable, building LAN should be up and running and you should be provided all the information required to correctly configure the lighting control devices, including:
11 +** Specific IP addresses or an IP address range for the lighting control system
12 +** Subnet mask
13 +** Default gateway/router IP address
14 +** Any specific hostnames required
11 11  * All Crestron hardware (processor panels, HUB panels, and load controllers) should be powered up and remain powered up
12 12  * All loads (fixtures) should be landed at load controlling modules according to the load schedule in the submittals
13 -** All loads should be powered up and verified that there are no shorts or tripped breakers
17 +** All loads should be powered up and verified that there are no shorts or tripped breakers 
14 14  ** Certain load controllers, such as CLX modules, will need the terminal jumpers removed prior to load verification
15 15  ** Loads should be tested to ensure that they are controlled by the correct modules and outputs
16 16  *** Most 0-10V modules have local buttons which can be used to test dimming and switching