4.1 | 1 | The foundations of a quick, easy, and trouble-free startup are laid before the control hardware even arrives onsite. Meeting with the electrical contractor prior to construction is important to establish a good working relationship, explain the requirements for a Crestron lighting control installation, and to exchange contact information so that any technical questions or concerns can be addressed prior to startup. |
![]() |
1.1 | 2 | |
3 | Though a pre-construction site-visit may seem like a wasted expense, by communicating expectations and requirements to the electrical contractor prior to startup you are actually able to save time and headache on-site. For large jobs especially, taking the time to ensure a proper installation will save hours or days during startup. Any time spent by a technician on-site tracking down serial numbers or troubleshooting/correcting a poor installation is a waste that could have been avoided with good communication and instruction prior to and throughout the installation process. | ||
4 | |||
![]() |
7.1 | 5 | Covering these important topics with the electrical contractor during the pre-construction phase is critical to smooth ShowRunnerCLC™ startups. |
![]() |
4.1 | 6 | |
![]() |
5.1 | 7 | Pre-construction topics to cover: |
![]() |
1.1 | 8 | |
![]() |
20.1 | 9 | * Wiring and Installation |
![]() |
1.1 | 10 | ** Do not power up panels until installation is complete and wiring is verified safe to connect |
![]() |
19.1 | 11 | ** [[Cresnet wiring>>doc:SHOWRUNNER™ Setup Guide.Troubleshooting Guide.Troubleshooting.Cresnet Wiring Overview.WebHome]] (for jobs with Cresnet) |
![]() |
9.1 | 12 | *** (% style="color:green" %)**DO**(%%) check for shorts before landing at the panel |
13 | *** (% style="color:green" %)**DO**(%%) land the shield with COM at the panel | ||
14 | *** (% style="color:green" %)**DO**(%%) splice through and insulate shield in the field | ||
15 | *** (% style="color:green" %)**DO**(%%) use wire nuts for Cresnet splices | ||
16 | *** (% style="color:red" %)**DO NOT**(%%) use lever-nuts for Cresnet splices | ||
17 | *** (% style="color:red" %)**DO NOT**(%%) leave copper showing at terminations | ||
18 | *** (% style="color:red" %)**DO NOT**(%%) excessively strip back the teal-yellow jacket | ||
![]() |
17.1 | 19 | ** [[Ethernet terminations>>doc:SHOWRUNNER™ Setup Guide.Troubleshooting Guide.Troubleshooting.Ethernet Wiring Overview.WebHome]] (where the EC is terminating the Ethernet) |
![]() |
11.1 | 20 | *** (% style="color:green" %)**DO**(%%) use standard, non-passthrough RJ-45 connectors |
![]() |
9.1 | 21 | *** (% style="color:green" %)**DO**(%%) use T568B Pin-Out |
![]() |
12.1 | 22 | *** (% style="color:red" %)**DO NOT**(%%) use EZ-style passthrough RJ-45 connectors |
![]() |
9.1 | 23 | *** (% style="color:red" %)**DO NOT**(%%) exceed 100m/328' cable length |
![]() |
18.1 | 24 | ** [[Zūm Wired wiring>>doc:SHOWRUNNER™ Setup Guide.Troubleshooting Guide.Troubleshooting.Zūm Wired Wiring Overview.WebHome]] (for Zūm Wired jobs) |
![]() |
11.1 | 25 | *** (% style="color:green" %)**DO**(%%) use standard, non-passthrough RJ-45 connectors |
![]() |
9.1 | 26 | *** (% style="color:green" %)**DO**(%%) use T568B Pin-Out |
![]() |
11.1 | 27 | *** (% style="color:red" %)**DO NOT**(%%) use EZ-style passthrough RJ-45 connectors |
![]() |
9.1 | 28 | *** (% style="color:red" %)**DO NOT**(%%) exceed 100m/328' cable length |
29 | *** (% style="color:red" %)**DO NOT**(%%) mix up Zūm Net and Zūm Link cables | ||
![]() |
1.1 | 30 | ** Follow the load schedule |
31 | * Serial number collection | ||
32 | ** SNs should be collected for all networked devices (all Cresnet devices and Zūm Wired devices) | ||
![]() |
2.1 | 33 | *** If possible, SNs should be provided prior to startup. This way they can be put into the configuration prior to arriving on-site |
![]() |
1.1 | 34 | ** The EC does not need to collect SNs for non-system devices (e.g. Crestron NS occupancy sensors, Steinel occupancy sensors, LDL photocells, and GLPPA-KP keypads |
35 | ** It is important to not just have a list of SNs on-site, but to be able to associate individual SNs with specific installed devices | ||
36 | ** The easiest way to do this is to write the SNs of installed devices on the floor plans or riser diagram as they are installed | ||
37 | * MAC address collection (optional) | ||
38 | ** Collecting MAC addresses is redundant if serial numbers are provided | ||
![]() |
3.1 | 39 | * Establish expectations for what "ready to commission" means by sharing the [[site readiness checklist>>doc:SHOWRUNNER™ Setup Guide.SHOWRUNNER™ Installation Guide.Preparation.Site Readiness Checklist.WebHome]] |